Situation > This was a seven story, interior tenant build-out for multi-use educational functional space.
Action > Scope included high-end millwork and flooring, all new MEP, HVAC, structural reinforcement throughout all rooms, plumbing, electrical, fire protection, and meeting spaces. FDOT turn lane improvements on adjacent US1 were also completed.
Results >This was an aggressive fast-tracked project completed in 7 months in order to be show ready for the grand opening party planned months in advance.